71/75 South - Dixie to Turfway Construction


plantmanky
 Share

Recommended Posts

Can anybody tell me what the construction going on is supposed to be for? All I have seen in a month is orange barrels. No work crews, no equipment, nothing that looks like work being done or has been done.

 

And down to ONE lane this morning!!

Link to comment
Share on other sites

They are working during the night time hours & on weekends to avoid impacting heavy traffic times. They are addressing 120 pavement sections along a 4-mile stretch. They are taking out bad pavement and replacing with new concrete.

 

Anything construction on the drive to the aquarium per #27 to interstate?